maintenance Day P+A 0800-1600. Will replace PLWCC1 element + check PMS mirrors. Fixing Nimbus bugs tied to PMS probes. Added conversion of XUVI.
Access time on C-130 extended due to network mirage - Data from rf01 posted to local archive special run for SAM.
ongoing question in FSSP - minor adjustment to layer size bins to increase diameter (16-30) Sharp drop off in particle unts between #7 & #8 leads to question of probe function - FSSP liquid water low in comparison with other sensors + DBARF also looking low. Will persue with Rogers + Irwin.