Project Tasks and Timeline

We have assigned particular areas of the development to each of us and identified major milestones in the implementation of this design. So far all we have is milestones, to which we have not yet assigned completion dates.

Table 1. Development Tasks and Milestones

AssignedTaskStatusDate
RichRadar display demoIn progress10 Feb
RichAccept delivery of 1U chassis with removable disks.Ordered 
RichSoftware RAID working in rack servers.PendingEarly March
 Spec and purchase of 100 baseT (1G baseT ?) ethernet hub.Not done 
 Purchase 100T Ethernet VME cards.Received--
AllSystem integration begins 10 Mar
GaryDemo the archiver writing to removable disks.In progresslate Feb
 First successful transfer of ELDORA DORADE over 100T ethernet to software clients on the 1U display and archive hosts. Requires modification of existing vxworks MCPL transmit code and the writing of the receive code on the display and archive hosts.  
GaryCompletion of data model software layer (DataSpace library) with which display and archiver will interface to receive and transmit data. Includes the shared memory (or equivalent) mechanism for distributing the data received off the network to clients within a single host.In progressEarly March
Rich and GaryFirst test of complete, integrated systemTBDMid March
Rich and GaryDeliver an updated operating procedures manual, documenting changes in operation instructions, changes in the look and use of the operator's display, and changes in detecting, diagnosing, and correcting problems with the new archiver and display.TBDMid April
AllTest flights for BAMEX begin. 12 May
AllBAMEX begins. 20 May