(Ongoing schedule adjustments are expected to accomodate future field deployments and potential funding limitations.) |
|||
| Interval | Task / Capability / Instrumentation | ||
| 18-Feb-05 to 9-Sep-05 | Critical Infrastructure Upload & Testing | ||
| Static Pressure (1) - High Rate Turbulence - HRT (25 sps) | |||
| Ambient Temperature (4) - Low Rate - LRT (1 sps) | |||
| Tropospheric Humidity (2) - LRT | |||
| Dynamic Pressure (2) - HRT | |||
| Differential Pressure (2) - HRT | |||
| Position - IRS / GPS - HRT (10 sps) | |||
| Aircraft Attitude - IRS - HRT | |||
| Aircraft Ground Speed - IRS / GPS - HRT (10 sps) | |||
| Aircraft Altitude - GPS / PALT - LRT | |||
| 3-D Wind Fields - HRT / clear air | |||
| 29-Sep-05 to 17-Nov-05 | Progressive Science Upload Period | ||
| "in-cabin" Community Exhaust | |||
| Simple Inlets (2) for Aerosols & Nonreactive Trace Gases | |||
| Dropsondes (4-channel receiver) | |||
| CN Concentrations - HRT | |||
| Differential GPS - HRT (10 sps) | |||
| Campos Chemistry - CO / CO2 - LRT | |||
| Stratospheric Humidity - LRT | |||
| Cabin Pressure - LRT | |||
| 18-Nov-05 to 23-Dec-05 | Progressive Science Research / Test Flights | ||
| Trailing Cone Reference Checks | |||
| Flow Mapping @ std apertures | |||
| 15-Jan-06 to 28-Feb-06 | T-REX Field Project - Upload, Test, Certification | ||
| 1-Mar-06 to 12-May-06 | T-REX Field Project - Flight Operations & Post Activities | ||
| 15-May-06 to 23-Jun-06 (tentative schedule) |
Gulfstream Warranty Work - Savannah, GA | ||
| 26-Jun-06 to 20-Oct-06 * (* tied to TTL-Chem Field Project) |
1st Infrastructure Upgrade Package
Aircraft Unavailable |
||
| "in-cabin" Compressed Gas Cylinder Mounts | |||
| Side View Window Blanks for Remote Sensing - pending | |||
| Wing Pylons for PMS style / size cannisters | |||
| Tail Deck Prep for radiometric sensors | |||
| Wing-to-Body Fairing modifications for radiometric sensors | |||
| SATCOM Real-time Data Link | |||
| Digital Video | |||
| Liquid Water / Total Water & Icing Rate | |||
| Optical Droplet & Aerosol Sizing | |||
| Counterflow Virtual Impactor - conditional | |||
| 23-Oct-06 to 16-Mar-07 | Open to Request | ||
| 19-Mar-07 to 11-May-07 (tentative schedle) |
2nd Infrastructure Upgrade Package
Aircraft Unavailable |
||
| Primary Optical View Ports (3) / Fused Silica | |||
| Retractable OV Port covers & defogging | |||
| Mission Scientist Station | |||
| LCS Cooling System | |||
| Radar Altimeter | |||
| Radiometric Surface Temperatures | |||
| Radiometric In-cloud Temperature | |||
| All Weather 3-D Wind Flux Pod - HRT | |||
| Temperature Fluxes (2) - HRT | |||
| Humidity Fluxes (2) - HRT | |||
| Laser Wind Velocimeter | |||
| 14-May-07 to 14-Sep-07 | Open to Request | ||
| 17-Sep-07 to 16-Nov-07 (tentative schedule) |
3rd Infrastructure Upgrade Package
Aircraft Unavailable |
||
| General / Large User Wing Pods (2) | |||
| Low Altitude Supplemental Cooling System | |||
| After 16-Nov-07 | Open to Request | ||